Off-Grid Solar & Batteries are an efficient power option for the Mining Industry due to the high costs associated with diesel/fuel fed generators.

However it’s critical to take the time to design, and engineer a stand alone power system fit for a remote mining operation, built for harsh Australian conditions. Key considerations include:

  • Load analysis, this is the process of identifying the loads/equipment/appliances which will be require energy to run, and of which will be supplied by the off-grid solar system
  • Days of autonomy, once we understand how much power the site equipment will consume, we can design a battery/solar system which will provide multiple days of autonomy, ensuring in poor weather, downtime is avoided which is a common observation in undersized stand alone power systems 
  • Maximum demand, our load analysis will indicate exactly what the peak requirement of the site is. CPP will build buffer into this maximum demand by designing a larger inverter system than what is currently required to allow for expansion. Batteries & solar panels are reasonably easy to expand/add onto a SAPS however changing inverter capacity is difficult once installed, especially once it’s in a highly remote location such as the Pilbara, Western Australia.
  • Backup diesel generator with automatic start, unless multiple days of battery autonomy and solar can be installed, a backup diesel generator will be required to charge the batteries when the state of charge is low. This can be programmed to automatically start

Available in either single phase or three phase. Customisable for AC or DC loads including 12V, 24V, 48V (DC) or 240V/415V (AC). Equipment can be either fan cooled or air-conditioned depending on site conditions and a specific energy assessment with the help of CPP’s design and engineering team. 